Practice: Valuing a Stream of Dated Payments
Question
Error diagnosis · Classification
A three-year contract pays
What is wrong?
2 hints available, least help first.
Hint 1: Retrieval cue
Write out when each payment arrives, in periods from today.
Hint 2: Concept cue
A flow at the end of year 1 is one period away. What exponent does that give?
Direct application
A project costs
Enter the value. It is checked against the answer and the precision this task asks for.
2 hints available, least help first.
Hint 1: Retrieval cue
Discount the year-5 receipt by
Hint 2: Next step
Direct application
A stream pays
Enter the value. It is checked against the answer and the precision this task asks for.
2 hints available, least help first.
Hint 1: Retrieval cue
Hint 2: Next step
Direct application · Comparison
Two mutually exclusive projects each cost
Error diagnosis
A mine has cash flows
Method selection
A utility must decide whether to build a treatment plant. The stream is a large outlay now, thirty years of net receipts, and a substantial decommissioning cost in year thirty-one. The regulator will accept the appraisal only if it states what discount rate was used and shows the result is robust across the plausible range for that rate. Which appraisal should be prepared?
Interpretation
At a discount rate of
Transfer · Evaluation
A research funder compares two programmes by the annualised percentage growth in citations each produced. Programme X, costing £40{,}000, grew citations
Construction · Evaluation · Explanation
A board is asked to approve one of two mutually exclusive proposals, and separately to record a liability. The finance note says:
- Proposal A: costs
now, returns at the end of year 1. Internal rate of return . - Proposal B: costs
now, returns at the end of year 5. Internal rate of return . - The note recommends A, "having the higher return".
- Separately, a site will require restoration: the project's flows are
now, at the end of year 1, at the end of year 2. The note reports an internal rate of and, comparing against the firm's cost of capital of , recommends rejection. - The firm's cost of capital is
for the restoration project and for the two proposals, reflecting different risk.
Work through the following.
- The recommendation on A and B. Compute net present value for each at
and state which the board should approve. Say what the internal rates do and do not establish. - The crossover. The ranking by net present value reverses at
. Explain why a reversal is possible at all, given that the internal rates do not change with the discount rate. - The restoration project. Assess the note's reasoning, computing net present value at
. - Sign changes. Explain what feature of the restoration stream produces the difficulty, and what should have been checked before an internal rate was quoted.
- What you would put in the note. State the figures and the caveats you would report for both decisions.
Write your answer, then compare it with the worked solution.
3 hints available, least help first.
Hint 1: Retrieval cue
For part 1, discount each receipt to today and subtract the outlay before comparing anything.
Hint 2: Concept cue
For part 2, ask which of the two quantities depends on the discount rate and which does not.
Hint 3: Strategy cue
For part 3, compute the net present value at the stated rate rather than reasoning from the quoted root.
Compare with the worked solution
Comparing does not record a result. Judging your own written answer cannot show that you can do this without help.
1. The recommendation on A and B. At the stated cost of capital of
B should be approved. It leaves the firm
Positive, so the project should be accepted, and the note's recommendation to reject is wrong. The reasoning fails because the rule "accept if the internal rate exceeds the cost of capital" assumes a stream whose net present value falls as the discount rate rises, true for a conventional investment, false here. This stream has NPV
A complete answer does each of these:
- ranks by net present value
- identifies multiple roots
- chooses criterion for decision
Construction · Direct application · Explanation
A contract pays
(a) Compute the present value of the five level payments at
(b) Add the year-8 payment and give the present value of the whole contract.
(c) Recompute the whole contract at
Write your answer, then compare it with the worked solution.
3 hints available, least help first.
Hint 1: Retrieval cue
Discount each flow by
Hint 2: Concept cue
The annuity formula sums a geometric series; it should reproduce the column exactly.
Hint 3: Strategy cue
In (c), compare the percentage fall of the annuity against that of the single late flow.
Compare with the worked solution
Comparing does not record a result. Judging your own written answer cannot show that you can do this without help.
(a) The five level payments at
| flow | present value | ||
|---|---|---|---|
| 1 | 200 | 0.943396 | 188.679 |
| 2 | 200 | 0.889996 | 177.999 |
| 3 | 200 | 0.839619 | 167.924 |
| 4 | 200 | 0.792094 | 158.419 |
| 5 | 200 | 0.747258 | 149.452 |
Sum:
By the annuity formula, since the flows are level and consecutive:
The two agree exactly. They must: the formula is the closed form of the geometric series the column computes, not an approximation of it.
(b) The whole contract. The year-8 payment is a single flow:
Note the timing convention: every flow arrives at the end of its year, so nothing is undiscounted. A flow at
(c) At
The value fell by
Why. The discount factor is
A complete answer does each of these:
- computes present value
- applies annuity formulas
Session complete
Every question in this set has been through once. What you can do now depends on how it went — practising again is worth more than moving on if any of it was uncertain.
Practice data
Your practice record is stored in this browser only. Clearing it removes every answer and every scheduled review, and cannot be undone.